Shoal Point Development, Mackay
​​ERSCON worked closely with the Developer and local authorities on the ongoing Shoal Point Development that includes 299 residential lots, 3 high density lots, a shopping village, and a resort site. Our company is committed to delivering quality work that meets our clients’ needs and can provide engineering support across multiple project aspects to ensure successful delivery.
Our involvement in the project has been extensive, spanning from initial feasibility estimates to detailed civil design, contract administration, and construction supervision. Major works include:
-
Design of Bulk earthworks across the site, approximately 200,000m3 cut to fill.
-
Detail design of all civil infrastructure on the first 3 stages (100 residential lots).
-
Superintendent role and construction inspections of bulk earthworks, first 2 stages of civil works (67 residential lots) and the entry road.
​
Additionally, we offer more detailed consulting services, which were particularly relevant for this project. We collaborated with multiple subconsultants to provide the following services:
-
Water Sensitive Urban Design (WSUD) Modelling using MUSIC.
-
WSUD design and supervision of bioretention basin construction.
-
Trunk sewer hydraulic modelling.
-
Trunk sewer infrastructure construction supervision (sewer pump stations and rising mains)
-
Contaminated land coordination to remove the site from the Environmental Management Register.
-
Rock Revetment design.
-
Coordination of coastal engineering erosion assessments and monitoring.
-
Coordination of blasting for bulk earthworks.
-
Cultural heritage liaison to gain approvals to clear the site.
​
​
​
​
​
​​
​
​
​
​
​
​
​
​
​
​
​
​